kelly_construction_logo_main-02.png
Corporate Headquarters

+1 869 760-1266 | St Kitts

Head Office

P.O. Box 2332, Basseterre, St. Kitts

Barbuda Airport Project Work In Progress

July 12, 2021

Kelly Construction has completed a substantial amount of work as its team of experts continue on schedule with the Barbuda Airport Project.

To date, forty percent (40%) of the airfield ground lighting (AGL) has been completed along with eighty percent (80%) of the runway sub-base. The asphalt plant has already arrived on Barbuda and paving of the runway is expected to begin in September 2021.

The team continues to work closely with the professionals of the Antigua and Barbuda Airport Authority (ABAA) with the shared goal of delivering a much-needed international airport on the island of Barbuda.

kelly_construction_logo_main-02.png
About Us

Your Premiere Construction Services Provider in the west Indies