Kelly Construction has been employed as the general contractor (GC) to complete the steel building erection for the reverse osmosis (RO) plant at Coco Point,

Kelly Construction has been employed as the general contractor (GC) to complete the steel building erection for the reverse osmosis (RO) plant at Coco Point,

Kelly Construction Antigua has completed the new runway for Barbuda Airport on schedule. All the AGL conduit and conductors have also been completed and the

Kelly Construction has completed a substantial amount of work as its team of experts continue on schedule with the Barbuda Airport Project.
To date, forty percent (40%) of the airfield ground lighting (AGL) has been completed along with eighty percent (80%) of the runway sub-base. The asphalt plant has already arrived on Barbuda and paving of the runway is expected to begin in September 2021.