Kelly Construction has completed a substantial amount of work as its team of experts continue on schedule with the Barbuda Airport Project.
To date, forty percent (40%) of the airfield ground lighting (AGL) has been completed along with eighty percent (80%) of the runway sub-base. The asphalt plant has already arrived on Barbuda and paving of the runway is expected to begin in September 2021.